Pecan Road section to be reconstructed starting Oct. 30

Team Radio Marketing Group - October 30, 2017 8:54 am

Beginning Monday, Oct. 30, work will begin to reconstruct a section of Pecan Road beginning south of the intersection of Lake Road and extending 200 feet south.

The existing deteriorated asphalt road is being replaced with new concrete pavement.  Construction is scheduled to take 21 calendar days, barring weather delays.

Pecan Road between Lake Road and Kelley Avenue (Big Snake Bridge) will be closed to through traffic for the duration of the project.  Traffic will be detoured to 14thStreet.

The City of Ponca City has entered into a contract with Hembree & Hodgson Construction, LLC of Ponca City, OK to perform this improvement project.

Any questions regarding this project may be directed to the City Engineering department at 763-8046.

 

Latest Stories

Biden heads into a make-or-break stretch for his imperiled presidential campaign

WASHINGTON (AP) — President Joe Biden on Thursday opened a critical stretch in his effort to salvage his imperiled reelection campaign, facing...

MAN SHOT BY DISPENSARY EMPLOYEE DURING ATTEMPTED BURGLARY, TULSA POLICE SAY

TULSA, Okla. – A man is injured after being shot at a shopping center overnight in Tulsa,...

Tunnel to Towers Pays Off Family Home of Edmond Officer Killed in Crash

EDMOND, OKLA. (KOKH) — In honor of Independence Day, Tunnel to Towers delivered 35 mortgage-free homes to...