Oklahoma veterans hospital work over budget, behind schedule

The Associated Press - March 25, 2018 10:31 am

(Information from: The Oklahoman, http://www.newsok.com)
OKLAHOMA CITY (AP) – An inspector general’s report says two construction projects at the Oklahoma City Veterans Affairs Medical Center are $10.8 million over budget and several years behind schedule.
The Oklahoman reports that the VA report released Friday reviewed construction of a new surgical intensive care unit and expansion of an operating room.
The report says poor workmanship has wasted money, greatly delayed the projects, and created safety concerns. In addition, unfinished construction on the hospital’s roof has been exposed to the elements and will have to be redone.
The report says the surgical unit project was fraught with failures and shoddy work. The report further states that both projects suffered from lack of oversight.
The VA has asked Congress to spend $10.8 million more to tear down part of what’s already been constructed and rebuild it.

 

Latest Stories

Festival of Angel Lights Opening November 26

Volunteers and Mr. and Mrs. Santa are gearing up for the Opening Night Event of Festival...

Adysen Thompson Named Miss NOC

Adysen Thompson of Prague, Oklahoma, was crowned Miss NOC Tuesday night at the Kinzer Performing Arts...

More People Surviving Lung Cancer, But Work Remains in Screening and Biomarker Testing

(TNND) — The lung cancer survival rate has improved 26% in the last five years, according to...